Many companies recognise that simulation modelling can significantly reduce the risk associated with major change. A recent project at Carlsberg-Tetley’s Northampton Brewery resulted in an envisaged requirement to install a third filter at a cost of £1m being avoided whilst the requirement to increase capacity by 33% was met. The best solution, identified through modelling, was not the obvious one.